Road Projects - December 5-9, 2022

From December 6, 2022 post.

ROAD PROJECTS - DECEMBER 5-9, 2022. 

Projects for the week of 12/05/2022-12/09/2022

District 1:

 • Camino a las Estrella’s drainage project will continue this week, crews will finish the installation of the drainage pipe and start to shape the road.

 • Crews will continue to mow the shoulders in the Placitas area.

District 5:

 • Crews will continue to install culverts and backfill San Pablo Rd. in the Cuba area.

 • Crews will be blading roads in the San Luis area.

*This is a tentative schedule and may change due to weather and down equipment.