CITY OF SANTA FE: Orange Barrel Report for the Week of November 22, 2020

Road

City of Santa Fe issued the following announcement on Nov. 20.

New:

Sunshine Plumbing: adding two water meter taps, and a fire line tap at 1372 Cerrillos Rd (next to Discount Tires). Lane closures and lane shifts will be in place, expect delays. Work is scheduled to begin 11-16-20 thru 11-27-20. Contact Joseph Santangelo at 505-480-4221for any questions.

On Going:

Klinger Construction: Building a new deceleration lane at 7521 Cerrillos Rd, with curb, gutter, sidewalks, and lane striping. Expect delays as the turning lane to get behind the new Wal-Mart will be blocked off. Work is scheduled to start 11/13/20 thru 12/31/20. Contact Jeffrey Slopek at 505-615-7646 for any questions.

Sub Surface Contracting: Removing and replacing the main water line on Camino Racheros, and Camino Ranchitos, El Caminito and a portion of Camino Del Monte Sol. Work will begin 11-4-20 thru 12-15-20 Contact Jeremey Sanderson (505) 690-1440 for any questions.

Klinger Construction: Single lane closed on Paseo De Peralta for construction From Washington Ave to Old Taos Highway. Traffic control will stay in place for the remainder of the project. Contact Kody Keelin at 505-231-4987 for any questions.

Kassam Construction: Will be finishing up with sidewalks, and drive entrances, and will be placing temporary striping on road. Traffic control will remain in place until striping is done. Contact Santiago Gonzales at 505-975-1391 for any questions.

GM Emulsion: Installing turn lanes, and widening Rufina St. at Camino Del Griego. Lane shifts, and detours will be in place. Work is ongoing, but may have delays through 12-31-20. Contact Angelo Gonzales at 505-471-9981 for any questions.

GM Emulsion: Construction of Rail Trail from Alta Vista Street to Pen Road and a trail connection at Monterey Drive to the Rail Trail. Work will begin 5-26-20 thru 12-31-20. Flaggers and *lane shifts will be in place. Contact Jeremy Martinez at 505-955-6931 for any questions.

GME General: Removing and resetting the sidewalk bricks along Washington Ave. to W. Palace. Work is scheduled to begin 8-5-20 thru 11-31-20. Contact Angelo Gonzales at 505-471-9981 for any questions.  

EMCO: Construction of bike lanes on both sides of Old Santa Fe Trail from E Zia Road south to City limits. Work will begin 5-26-20 thru 11-30-20. Flaggers and lane shifts will be in place. Contact Jeremy Martinez at 505-955-6931 for any questions.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS